Gantt Chart & Budgeting

Gantt Chart

This estimated Gantt Chart shows the design tasks and its estimated start to end date. The black on the chart is our main tasks, blue is sub tasks, and green is our final design presentation and proposal. The red line shows the critical path of this LID design.Gantt Chart Upgrade

This figure shows the actual Gantt Chart for the LID design. Because of the time conflict on the lab access, the team could only use the Fall 2017 semester to do testing. The red arrows in the Actual Gantt Chart show the tasks that were pushed back.

Design Hours & Budgeting

This shows the comparison of design hours and cost between estimate and actual design process. Overall, the estimated hours and actual hours are close, but the actual cost is lower than estimated.

Overhead

This is the overhead for our tean on each team position.